PROJECT AUTHORIZATION PACKET ID: PMT-QH1N
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
6780812R 6780808U 6780808D    67808 30
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER
100 046 1 000-004

NHPP 4611 009

08-00059
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
MAJOR WIDENING MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL FHWA STATE KYTC LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
8-59.25 D 1100 FD52 2019 2020 $1,000,000.00
8-59.25 D 1200 FD52 2019 2020 Z001 $1,000,000.00
8-59.25 R 1100 FD52 2019 2020 $1,000,000.00
8-59.25 R 1200 FD52 2019 2020 Z001 $3,479,700.00
8-59.25 U 1200 FD52 2019 2020 Z001 $4,620,000.00
8-59.25 U 1100 FD52 2019 2020 $1,155,000.00
CURRENT FUNDING REQUEST TOTAL: $12,254,700.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $29,591,359.00
UTILITIES $11,395,928.00
R/W $36,129,700.00
CONSTRUCTION $60,915,888.00
NON-HIGHWAYS $0.00
  Total: $138,032,875.00
REMARKS: "BUILD GRANT PROJECT" THIS AUTHORIZATION PROVIDES FEDERAL NHPP FUNDS FOR FINAL DESIGN SERVICES, R/W ACQUISITIONS, AND UTILITY ADJUSTMENTS. STATE FD04 FUNDS WILL BE USED FOR FEDERAL MATCH. TJ
 
Project Approval Recommended By:
John Moore   8/30/2019
Signed and Approved by:
Andy Barber   9/3/2019
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
08-00059.25 PULASKI


8 SOMERSET NORTHERN BYPASS KY 461 MI IMPROVE KY-461 FROM KY-80 TO BUCK CREEK BRIDGE, INCLUDING INTERCHANGE AT KY-80. (18CCR)